Park News
It
has been confirmed that there is a Woodcock nesting in the park.
73
acres by Mt. Lucia
has been burned. There was an addition 20 acres that they were hoping to get
done but the winds did not cooperate. Ranger Kevin has been assisting with other
burns in the area.
Organizational News
The Friends of Stone Park meet the 3rd Tuesday of every month at 7 PM at the Dorothy Pecaut Nature
Center. All are welcome!
Campground Improvement Project Completed
Thanks to support from Regina Roth, John Gleeson, Jolly Time Popcorn, L & L Builders and numerous community
supporters, our Campground Improvement Project has been totally funded.
The project includes construction of two log cabins, a separate youth campground and renovation of the original campground. Construction
of the cabins and the youth campground have been completed. $137,000 from the Iowa Values Fund spearheaded the local
match fundraising campaign.
No financial contributions went to administration, consultants or project design. 100% of the money donated
to our campground improvement project went to construction. Call Greg Hoversten, Steering Committee Chairman at 251-0542
for more information.
Renovation of the existing campground is completed. The old shower building was demolished and a new
facility has been constructed. Upgrading of improvements as well as landscaping is to be completed this Spring (2008).
Cabin and shelter reservations can be made at https://eservices.iowa.gov/iowaparks/ .